Skip to content
Harrow Mechanical

Projects

Projects / Truganina, Victoria

Truganina data centre mechanical package

Head contractor, data centre sector

Contract value
$4,150,000
Duration
18 months
Sector
Data centre
Systems
Mechanical, Hydraulic, Controls, Commissioning
Completed
2026
Air cooled chiller units and pipework on a rooftop plant deck

Brief

Mechanical package for a new build facility of 4.5MW IT load across two data halls, delivered to a concurrently maintainable design.

Systems installed

  • 4 × 1,100kW air cooled chillers, N+1, on a common primary variable flow header
  • 24 × chilled water in row cooling units, 2.4MW sensible per hall
  • 2 × 60,000 litre thermal storage tanks giving five minutes of ride through at design load
  • 940m of dual path chilled water reticulation, DN250 to DN80, welded and tested to AS 4041
  • Dual redundant BMS controllers with concurrently maintainable sequences on every isolation point
Dual redundant BMS controller cabinet with labelled cable terminations

Constraints

Nothing in the chilled water system could be isolated in a way that dropped a hall, so every valve, pump and controller was proved twice: once on paper against the isolation schedule before pressure test, then again live under load. The integrated systems test was booked with the incoming tenant twelve months out as a fixed two week window, which put every preceding milestone on a date rather than a float, including a single 400 tonne crane day for the four chillers and both storage tanks.

Outcome

Integrated systems testing ran eleven days in February 2026 at 100% of design IT load on 4.5MW of load banks. All 42 failure scenarios were executed with no cold aisle exceeding 27°C. Commissioning records issued to AIRAH DA19 with the isolation schedule as a handover document.