Projects / Laverton North, Victoria

Laverton North distribution centre

Head contractor, industrial sector

Contract value
$3,400,000
Duration
15 months
Sector
Industrial
Systems
Mechanical, Hydraulic, Controls
Completed
2025
Ceiling mounted evaporators and ductwork above racking aisles

Brief

Mechanical and hydraulic services to a 38,000 distribution facility with a 4,200 chilled pick face and a two level office.

Systems installed

  • 3 × 900kW low charge ammonia packaged chillers to AS/NZS 5149
  • 12 × 62kW ceiling mounted evaporators holding the 4,200 m² pick face at 4°C
  • 6 × smoke exhaust fans, 12 m³/s each, rated 300°C for 60 minutes to AS 1668.1
  • 220kW of office VRF across two levels with after hours metering per tenancy
  • 1,400m of DN100 to DN300 trade waste and roof drainage to AS/NZS 3500
Warehouse roof with smoke exhaust fans and condensing plant

Constraints

Lease commencement was fixed twelve months before practical completion and the tenant racking installer had a contracted start that could not move, so roof plant, smoke exhaust and the pick face refrigeration all had to be complete and pressure tested before racking took the floor. Eleven weeks were lost to a wet spring early in the program. The balance was recovered by splitting the pick face and office packages across two crews on staggered six day weeks, with the smoke exhaust fans installed from the roof rather than from below to keep the floor clear.

Outcome

Practical completion 8 August 2025, two days inside the contract date. Pick face pull down from ambient to 4°C recorded at 19 hours with dock doors sealed. Smoke exhaust performance witnessed by the building surveyor and included in the essential safety measures schedule issued with the occupancy permit.